Weekly Update: April 8-14th

Shaft #1 Regional Road 56 and Golf Club Road
-the contractor has stopped tunnelling from Shaft #1 to Shaft #2 and is widening the tunnel for construction purposes. The work is scheduled to be completed this week, they will then begin to prepare for the resumption of tunneling.
Shaft #3 Golf Club Road and Trinity Church Road
-Shaft excavation is ongoing.
Shaft #4 Dickenson Road and Nebo Road
-Excavation of the rock in shaft is starting Wednesday April 10 for the next few weeks.
Shaft #5 - Dickenson Road, approximately 385m east of Glover Rd
-contractor is continuing with drilling the secant piles at this location.
Shaft #6 Dickenson Road and Nebo Road
-no work scheduled at this location
Open Cut Sewers – Miles Road to Upper James
-Subcontractor is mobilizing onsite this week. They will be resuming the sewer construction beginning Thursday April 18, 2024.