Development Update: Dickenson Sanitary Trunk Sewer
- Crista Cooper
- Apr 11, 2024
- 1 min read
Weekly Update: April 8-14th

Shaft #1 Â Â Â Regional Road 56 and Golf Club Road
-the contractor has stopped tunnelling from Shaft #1 to Shaft #2 and is widening the tunnel for construction purposes. The work is scheduled to be completed this week, they will then begin to prepare for the resumption of tunneling. Â
 Shaft #3     Golf Club Road and Trinity Church Road
-Shaft excavation is ongoing. Â
Shaft #4Â Â Â Â Dickenson Road and Nebo Road
-Excavation of the rock in shaft is starting Wednesday April 10 for the next few weeks.Â
Shaft #5Â - Dickenson Road, approximately 385m east of Glover Rd
-contractor is continuing with drilling the secant piles at this location.
Shaft #6Â Â Â Dickenson Road and Nebo Road
-no work scheduled at this location
Open Cut Sewers – Miles Road to Upper James
-Subcontractor is mobilizing onsite this week. They will be resuming the sewer construction beginning Thursday April 18, 2024.