Development Update: Dickenson Sanitary Trunk Sewer

Weekly Update: April 8-14th



map of dickenson sanitary trunk sewer


Shaft #1    Regional Road 56 and Golf Club Road

-the contractor has stopped tunnelling from Shaft #1 to Shaft #2 and is widening the tunnel for construction purposes.  The work is scheduled to be completed this week, they will then begin to prepare for the resumption of tunneling.   


 Shaft #3      Golf Club Road and Trinity Church Road

-Shaft excavation is ongoing.   


Shaft #4     Dickenson Road and Nebo Road

-Excavation of the rock in shaft is starting Wednesday April 10 for the next few weeks. 


Shaft #5 - Dickenson Road, approximately 385m east of Glover Rd

-contractor is continuing with drilling the secant piles at this location.


Shaft #6    Dickenson Road and Nebo Road

-no work scheduled at this location


Open Cut Sewers – Miles Road to Upper James

-Subcontractor is mobilizing onsite this week.  They will be resuming the sewer construction beginning Thursday April 18, 2024.


Information on the Development of the Dickenson Road Sanitary Sewer project can be found here: