top of page

Ward 11 Rural Road Projects this summer

The City of Hamilton has a contract with Cornell Construction Ltd. to perform preventative maintenance on the following roads as called for under contract C15-46-15.  the Surface Treatment program contributes to reduced maintenance costs, dust mitigation and extended road lifecycle expectancy.  Construction is scheduled to commence on or about June 15, 2015, with a completion date of August 31, 2015, weather permitting.

Street Name                       From                          To 

Leeming Road                                  Hwy #6                                 Ferris Road

Eighth Road East                             Ridge Road                         850 S of Ridge Road

Purdy Crescent                                 Mud Street                         East Townline Road

Tenth Road East                              Highland Road East         Mud Street East

Cemetery Road                                 Fletcher Road                    Hwy #56





The work involves, pulverizing followed by Double Surface Treatment application, (Tar and Chip).  You may experience some inconveniences such as noise, dust and restricted traffic movement during construction.  It is intended to maintain pedestrian access and vehicular access to all properties on these roads at all times through construction; however, there will be certain times that access will be restricted.  Every effort will be made to do the work in a timely manner and to keep any inconvenience to a minimum.  We ask for your patience during this period.

For the duration of the project, the City of Hamilton on-site inspector will be made available to explain the sequence of work and make note of any anticipated problems during construction.

City staff contacts are:

Paul Murray, on-site inspector    289-260-9100

Derek Sohail, project manager    905-546-2424, ext 2929

or as always, you can contact me

Comentarios


bottom of page