Here is the schedule for this week:
Shaft #1 Regional Road 56 and Golf Club Road
-tunneling from shaft #1 to Shaft #2 is ongoing, contractor is working 2 shifts. The machine is between MH43A and MH42A (#3328 & #3219 Golf Club Road)
-no work at this location, single lane of traffic is open to residents at this location.
Shaft #3 Golf Club Road and Trinity Church Road
-the contractor is continuing to mobilize the Micro-tunneling equipment to this location
Shaft #4 Dickenson Road and Nebo Road
-the contractor is waiting on repairs to the equipment, work will resume once repairs are completed (no time line indicated on repair time)
Shaft #5 - Dickenson Road, approximately 385m east of Glover Rd
-no work scheduled at this location
Shaft #6 Dickenson Road and Nebo Road
-no work scheduled at this location
Maintenance Hole 32A Dickenson Road and Glover Road
-no further work at this location this week
Maintenance Hole 33A Dickenson Road between Trinity Church Road and Glover Road
-no further work at this location this week
Maintenance Hole 26A Dickenson Road between Miles Rd and Nebo Road
-no further work at this location this week
Maintenance Hole 27A Dickenson Road between Miles Rd and Nebo Road
- Drilling has stopped due to equipment breakdown. Repairs are still being completed
Open Cut Sewers – Miles Road to Upper James
-Subcontractor is installing the sewer pipe in the open cut trench in the vicinity of #8472 and #8468 Dickenson
All road closures still remain in effect, Miles Road to Upper James on Dickenson is closed to thru traffic, travel is still open for residents, city services, EMS and school buses. Communication is being made with city services, EMS and school buses when the closure points are moved as the work progressed westerly towards Upper James.