The following are the time lines for resurfacing Twenty Rd in Mount Hope from Upper James to Glancaster Road.

  1. Installation of Culverts will be completed on July 04, 2014.

  2. Ditching  is scheduled to be completed during week of July 21, 2014.

  3. Resurfacing is scheduled to be completed during week of July 28, 2014.