March, 2015 Phase 1A – Dartnall Road to Upper Red Hill Valley Parkway (URHVP). – watermain installation from Nebo Road to Dartnall Road was completed and put into service last year – Dartnall Road/Rymal Road intersection reconstruction was completed last year – Contractor (Coco Paving) has resumed work this year and are currently replacing the concrete box culvert at the Glover Road/Rymal Road intersection. – balance of the construction works will be completed this year (road to binder asphalt) and the surface course asphalt to be placed in 2016

Phase 1B – URHVP to Fletcher Road – this phase of the construction was tendered and was recently awarded to Amico Infrastructure – contractor anticipates commencing construction in April – reconstruction of this section of road to binder asphalt is to be completed by the end of this year and the surface course asphalt to be placed in 2016

Public Works is administrating th econstruction on both projects. If you have any questions about the project please do not hesitate to contact my office.

0 views0 comments

Recent Posts

See All

Comments


bottom of page