Mt. Hope Community Park Update

The work is almost completed. We had hoped for completion before this long weekend but unfortunately there were a few weather and fabrication delays.

The contractor is finishing up installation of the boardwalk component of the project today. He will be using the remainder of this week and likely all of next week to fine grade, seed, sod and load and haul the excess material stockpiled in the parking lot.

The work areas that are currently fenced off will remain fenced until that time that the works are complete, which we anticipate being Friday May 28, 2021, assuming we do not experience any rain/weather delays.