Dickenson Road Sanitary Sewer Weekly Update: July 16th



Here is the schedule for this week:

 

Shaft #1    Regional Road 56 and Golf Club Road

-tunneling from shaft #1 to Shaft #2 is ongoing, contractor is working 2 shifts

Shaft #2   Located west of house #3458 Golf Club Road

-no work at this location, single lane of traffic is open to residents at this location.

 Shaft #3      Golf Club Road and Trinity Church Road

-the contractor is continuing to mobilize the Microtunneling equipment to this location   

Shaft #4     Dickenson Road and Nebo Road

-the contractor will be drilling and breaking rock to advance the starter tunnel

Shaft #5 - Dickenson Road, approximately 385m east of Glover Rd

-the contractor will be excavating the rock from the shaft

Shaft #6    Dickenson Road and Nebo Road

-no work scheduled at this location

Maintenance Hole 32A   Dickenson Road and Glover Road

-no work at this location

Maintenance Hole 33A  Dickenson Road between Trinity Church Road and Glover Road

-rock drilling will be ongoing this week

Open Cut Sewers – Miles Road to Upper James

-Subcontractor is installing the sewer pipe in the open cut trench (currently working between #8382 and  #8374 Dickenson Road).  The open cut sewer work is now 70% completed.

   

All road closures still remain in effect, Miles Road to Upper James on Dickenson is closed to thru traffic, travel is still open for residents, city services, EMS and school buses. 


Communication is being made with city services, EMS and school buses when the closure points are moved as the work progressed westerly towards Upper James.