The following are the time lines for resurfacing Twenty Rd in Mount Hope from Upper James to Glancaster Road.

  • Installation of Culverts will be completed on July 04, 2014.
  • Ditching  is scheduled to be completed during week of July 21, 2014.
  • Resurfacing is scheduled to be completed during week of July 28, 2014.